Z70 WARRICK NORTH TO PIGEON CREEK Transmission

CenterPoint Energy

Client CenterPoint Energy
Completion Date 2021
Location Indiana
Completed by High Country Line Construction, Inc.

High Country Line Construction crews constructed 24 miles of new 138kV transmission line near Evansville, IN. The scope included new 466 steel monopole, single-circuit structures, and 39 double circuits and included installing 954 kcmil ACSR.